BUILDING A SOLAR HOUSE IN FRANCE - WEEK 7 - finishing monomur walls ready for roof »  Viewing charpente01     [Image 21 of 21]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      You have reached the last slide You have reached the last slide  
Comment: ArchiCAD image of the oak frame and trusses before the roof goes on, discussed with Mr Mazieres. He will order the oak and start making the frame soon. But how soon ?
The 4000 litre rain water cistern was brought and lowered into place place by Faye's Manitou. and the rest of the waterproofing sheet fixed in place.

The Manitou shovel with telescopic bucket putting sand around the waterproofing and over the drains.

The second lorry load of stone to fill under the auvent (roofed area linking house and garage)

Francis' assistant (today the lorry driver) removing the shuttering by the hole for the staircase down to the sous sol.

View fom South as it was left on Tuesday evening.

It rained quite hard on Tuesday and I worked alongside Francis who came in the afternoon without anyone else, directing him where to place stone and sand, and sometimes having to manually move rocks.

Francis ended the day by picking up all the roots of trees to the bottom of the land down the hill to form a vegetative boundary.

The sun came out on Thursday morning and I had a meeting on site with Mr Mazieres of Firbeix, the carpenter and roofer.  I delivered fial drawings of the oak frame and trusses and we discussed how to to put it up, probably in September (builders go on holiday for most of August)