Building a solar House in France - plastering, stone wall, septic tank and sand filter »  Viewing imgp0629     [Image 24 of 36]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: Wall nearing completion on Friday.
Laying out the perforated pipes over the gravel layer.

The geotextile was wrapped over the gravel covering the piping and then covered with soil.

The projecting end of the stone wall forms a plinth on which the main living floor of the house sits, and will screen a little terrace outside the guest bedroom..

View from the north.

Francis laying out the piping to the septic tank.

Next slide
 
Apr 18, 2008 - 04:17 PM
Rain continued, and the masons were not happy.

Pipework to fosse bedded on a bit of concrete here and there, and covered with sand. Luckily no trenches were needed and it was all covered with topsoil to a depth sufficient to protect it.

By Friday afternoon the site around the house looked like a battlefield.

The ventilation of the fosse as required by Mme Berthome.

The guest bedroom was plastered on Friday afternoon,

Album last updated on Feb 02, 2009 - 04:23 PM