Solar House In France - weeks 17 - 20 - interiors and electrical »  Viewing imgp0436     [Image 16 of 21]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: Another temporary landing on the mezzanine that I made quickly out of leftover poplar floor boards to make the access at the top of the temporary stair (echelle de meunier) safer. Note the rolls of 17 layer multi reflective insulation that I am using in a few places where the depth is insufficient for 300 cm of hemp insulation, and where the reccommendation that the wall or roof must "breathe" is not strictly required.
I have made a temporary landing at the top of the stairs down to the sous sol using leftover and reject poplar floor boards, and plan to make a temporary stair soon to make movement between floors easier and safer.

The electrician started work the day after the insulation was delivered to keep just ahead of the plasterer.  All the conduits and wiring that had to go behind the sloping ceilings had to be put in - also the conduits for plugs, lights and switches in the external monomur walls and sous-sol ceilings have to be fixed. He is going at an impressive rate and should finish the basics in a few days. We had to dash into Perigueux on Wednesday to choose fittings at Leroy Merlin and CGED.

I made the framing around the chimney duct and cupboard for the solar hot water tank in the spare bedroom.  All the partition framing that affects the plasterboard ceiling has to be in by Monday morning.

A few days after the electrician started, we had high winds and rain which revealed some serious leaks in the flashings around the monopitch roof light (chien assise).  The roofer had not followed my detail, and had cut the roofing felt ( a microporous but waterproof reinforced material) too short, and had not turned it up behind the zinc flashing.  With a strong wind behind it rain blew  uphill and over the edges of the tiles !

Another point where the back of a tile had been cut where it had to go round the oak post, losing the turnup at the back edge which would normally catch most of the water. This was the point of the the worst leak.   Mr Mazières was summoned urgently and came after the Easter weekend holiday and promised to rectify the fault.

Next slide
 
The roof has a series of leaks under the windows here when the wind blows a gale.

Partitions in the mezzanine, behind which is the roof space over the entrance and wc, which will be stuffed with hemp insulation.

The hemp semi rigid panels which are proving very difficult to cut.

The sous-sol atelier with the plasterers' scaffolding ready to start on Monday April 1st.

View of house from the south west at 6 at the end of March.