4: Margaret with her finger in a hole in the monomur (to be later plugged with insulation).
Unfolding took 2 hours with snags as the crane hook tangled and it had to be folded again.

Finally it was up, towering above the trees.  It was really because we did not want to cut trees near the house to create a prairie in which to build the house and leave lots of space for materials to be parked and vehicles to circulate, that Francis used to persuade me that he needed the crane at no extra expense.

The crane towering over the neighbourhood. A bit over the top for our our little house.

Fully erect and loaded with counterbalancing concrete blocks (10 tonnes)

The monomur walls rise on Tuesday morning

Next slide
 
Apr 17, 2007 - 08:22 PM
An adjustment to the height of the blockwork retaining wall.

Cedric fitting the temporary electricity supply box to the pole, Tuesday afternoon.

Francis using the remote control of the crane bringing down a palette of briques.

I am now convinced that the crane does speed up the job considerably.  All the blockwork and monomur could not have gone up so fast with only 2 men without it.

Rolling the glue onto the briques immediately before placing the next one - much quicker than laying concrete blockwork.