BUILDING A SOLAR HOUSE IN FRANCE - WEEK 11 - Roofing »  Viewing imgp9866     [Image 5 of 30]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: By 4 pm most of the rafters had been fixed and were being trimmed at the ends of the tie beams (entraits).
The last purlins being lowered with the 'Merlo' crane at full extension of 19 metres.

Placing rafters on the south slope.

Rafters fixed to the south slope.  A lot of discussion about the roof projection at each end.

Just before lunch rafters had been fixed on the south roof slope.  I went off to collect sample of larch boarding from Mr Merle in La Coquille.

Next slide
 
imgp9866.jpg - 2560 x 1920 - (3.31MB)
Oct 22, 2007 - 05:12 PM
In the afternoon it began to cloud over, but good weather is forecast for tomorrow. I hope Mr Mazieres can get the ecran de toiture and battens on before it rains again.

On Tuesdy afternoon the roof tiles arrived. Mr Mazieres and his men could not come and I was working on site marking out floor joist positions and trying to decide whether fixing the joists was a job I could do to save money.  But the joists are so heavy that I decided to leave to him and his men.

The floor joists under the mezzanine are oak, and will be dropped into the slots cut in the beams on the left. They are on the floor in the centre, being walked all over. I hope that it does not rain before the roof is covered, because oak shows black water marks that are hard to clean off.

Another job I had to do was to uncover the places where holes can be drilled through the concrete slab for pipes and other services.  I had placed blocks of polystyrene there before the slab was poured, where holes would miss reinforcing or precast beams.

Mr Mazieres and gang came back on Thursday and completed the rafters and fitted fascias.

Album last updated on Nov 01, 2007 - 01:31 PM