4: Sliding the forks into a pallette of 'briques' - the crane is operated by the remote control on Francis' belt.
Laying the 9th course Wednesday PM

Friday morning - laying the lintel course. The leaves on the trees have come right out in the last week - compare with photos taken a week ago.

Lintel 'briques' ready for concrete to be poured around reinforcing.

Briques at window opening. The hole is for vertical reinforcing.

View of North West wall on Friday - complete to receive the floor beams on Tuesday when the concrete block retaining walls are up to the same level/.